Agenda item

Civic Centre Integrated Impact Assessment (IIA)

To consider the report of Corporate Director Regeneration and Community Services.

Minutes:

Members considered the report of the Corporate Director of Regeneration & Community Services.

 

Following a discussion, the following actions were agreed:

 

ØThe final costs associated with the demolition of the Civic Centre be provided.

ØUpdated footfall figures relating to visits to all the community hubs be provided for February – June 2023 including the nature of usage and how residents were interacting through these channels.

ØThe report relating to the new Council Operating Model which was agreed at Council on 25th March, 2021 be circulated.

ØFurther information be provided in relation to parking/access issues, specifically disabled access at community hubs.

ØVisitor footfall in Ebbw Vale Town Centre to be provided.

 

It was, thereupon, unanimously,

 

RESOLVED, subject to the foregoing, that the report be accepted and it was confirmed that the Committee was assured that an Integrated Impact Assessment had been completed in line with legislation to be formally agreed at Council.

 