10 Review of Highway Capital Works Programme 2017 – 2022 PDF 526 KB
To consider the report of the Head of
Community Services.
Additional documents:
Minutes:
Consideration was given to report of the Head of Community Services.
The Committee AGREED to recommend that in the event that funding becomes available the following options be proposed:
Option 2b was the Members’ preferred option.
Option 2a: Highest Priority Classified Roads (ranked in order of priority) Estimated Total Cost £500,000
1. A467 Warm Turn Carriageway Resurfacing £75k
2. Tafarnaubach Ind Est (Top Road) Resurfacing £175k
3. Blaenant Ind Est Roundabout Resurfacing £75k
4. Big Arch / Steelworks Road / GO Resurfacing £50k
5. A4046 - Waun-Y-Pound Road, Ebbw Vale £25k
6. College Road, Ebbw Vale £100k
Option 2b As Option 2a plus 5 worst Residential Roads & Other Highway Related Works – Estimated Total Cost £1,000,000
Residential Roads: 5no priority residential roads £350k
Other Highway Related Works: -
· Crash Barriers £50k
· Road Markings, signs and bollards £35k
· Speed Humps £50k
· Traffic Order Reviews £15k
Options 2a & 2b may vary subject to the level of funding that may be made available.