Issue - meetings

Review of Highway Capital Works Programme 2017 – 2022

Meeting: 20/09/2022 - Place Scrutiny Committee (Item 10)

10 Review of Highway Capital Works Programme 2017 – 2022 pdf icon PDF 526 KB

To consider the report of the Head of Community Services.

Additional documents:

Minutes:

Consideration was given to report of the Head of Community Services.

 

The Committee AGREED to recommend that in the event that funding becomes available the following options be proposed:

 

Option 2b was the Members’ preferred option.

 

Option 2a: Highest Priority Classified Roads (ranked in order of priority) Estimated Total Cost £500,000

 

1. A467 Warm Turn Carriageway Resurfacing £75k

2. Tafarnaubach Ind Est (Top Road) Resurfacing £175k

3. Blaenant Ind Est Roundabout Resurfacing £75k

4. Big Arch / Steelworks Road / GO Resurfacing £50k

5. A4046 - Waun-Y-Pound Road, Ebbw Vale £25k

6. College Road, Ebbw Vale £100k

 

Option 2b As Option 2a plus 5 worst Residential Roads & Other Highway Related Works Estimated Total Cost £1,000,000

 

Residential Roads: 5no priority residential roads £350k

Other Highway Related Works: -

·        Crash Barriers £50k

·        Road Markings, signs and bollards £35k

·        Speed Humps £50k

·        Traffic Order Reviews £15k

 

Options 2a & 2b may vary subject to the level of funding that may be made available.