4 Planning Applications Report PDF 1 MB
To consider the report of the Team Manager Development Management.
Minutes:
Consideration was given to the following:-
C/2020/0301
Unit 19, Rassau Ind Est, Rassau, Ebbw Vale
Erection of 1 Wind Turbine and
Associated Infrastructure
The Team Leader Development Management gave an overview of the area in which the wind turbine would be erected with the assistance of visual aids.
The Officer informed Members that an application had been granted in 2019 to erect a single wind turbine at Unit 18, however this was no longer being built as planning permission for the erection of a Synchronous Condenser plant on the same site had been made and was under construction. Therefore, the developer was now applying for planning permission for a single wind turbine at Unit 19, Rassau Industrial Estate.
The site was in the middle of Rassau Industrial Estate, to the north/north west was open countryside which formed a buffer between the built up area and the boundary of Brecon Beacons National Park. The residential area of Rassau was located beyond to the south, southeast and southwest at a distance of approximately 400m away. The lower level of the estate was separated by the recently realigned A465 and a tree belt. To the east of the Industrial Estate approximately 1 km away was Garnlydan which was a similar elevation to the proposed turbine.
The Officer noted that
there was already two wind turbines
74m and 77m
in height on the estate approximately
550 metres to the south-west and 650m
to the north-east respectively and these were highlighted on the
visual aids presented. The Planning Statement confirmed that the
turbine would be subject to two or more regular maintenance visits
per year. The proposed dimensions are the same as those previously
approved at Unit 18. The proposal included a small building to
house a transformer, associated switchgear and electrical
protection equipment and be located close to the base of the
turbine tower and connected to the grid connection point via
underground cabling. The proposed turbine would supply power
directly to the nearby Yuassa Battery
(UK) Ltd manufacturing facility. The
Officer added that no details had been provided in relation to the
small building with this application, however the layout/design
plans would need to be provided to the Planning Department prior to
development.
The Officer outlined the internal and external consultation responses as detailed in the report. It was reported that the technical query raised had been addressed by the Agent and the Brecon Beacons National Park had submitted an objection in respect of the cumulative impact on the special qualities of the National Park area. It was also noted that one objection was received by a member of the public in relation to noise.
A detailed overview was provided of the Planning Assessment and the Officer noted key main points in relation to the following:-
· Welsh Government’s commitment to Generating Renewable Energy
· Policy 18 - Pre-Assessed Areas for Wind Energy
· Policy 17 – Renewable and Low Carbon Energy and Associated Infrastructure
· Principle if development on a primary employment site
· Landscape ... view the full minutes text for item 4